Die neue und alte Kabine der Fellhornbahn
Die neue und alte Kabine der Fellhornbahn
Modernization of the
Fellhorn cable car I
Modernization of the Fellhornbahn I

The Fellhornbahn I will be faster, more comfortable, and more impressive.

After extensive overhaul work in 2024, the cable car will receive new cabins, state-of-the-art control technology, and a facelift of the stations in spring/summer 2025.

What does this mean?
• Shorter travel times
• Less waiting time
• A ride like an airplane – quiet, floating, and with even more panoramic views

The Fellhornbahn II will remain in operation as usual during the work.

Successful inauguration: 50 years of the Fellhornbahn
x
Der Inhalt wird von Youtube bereit gestellt. Mit dem klicken auf den Playbutton werden ggf. personenbezogene Daten verarbeitet und Cookies gesetzt.
Construction diary of the Fellhornbahn I
2024
Beiträge aus dem Q1 2024
Beiträge aus dem Q2 2024
Beiträge aus dem Q3 2024
Beiträge aus dem Q4 2024
Upgrading of the aerial tramway in Section 1
1st construction phase: May 13 to July 5, 2024
The cabins are lifted by the rope
Moving the supporting cables
Factory revision
Re-bearing of the drive pulleys
Gearbox overhaul
2025
Beiträge aus dem Q1 2025
Last day of operation of the Fellhornbahn I
2nd construction phase from 31 March 2025; duration approx. 14 weeks
Last transport trips on section 1 with old control
Removal of all technology from the engine room
Helicopter material flights to supports 1 and 2
Assembly of the main drive, brakes, emergency diesel and hydraulics
Delivery and replacement of the new cabins
Reopening of Fellhornbahn I
Upgraded aerial tramway with new cabins goes into summer season as planned
Construction phase completed
08/25/2025
Construction phase completed

The modernized Fellhornbahn I cable car successfully opened as planned at the beginning of August 2025 and now shines in its new splendor. Perhaps the biggest highlight of the new cable car: the floor-to-ceiling Plexiglas walls allow for a magnificent panoramic view while riding in the cabin.

A heartfelt thank you goes to all project participants, partners, and employees who contributed with great commitment to the successful implementation. We also thank our guests for their patience during the construction phase.

We look forward to the rest of the summer season with many enthusiastic visitors!

08/08/2025
Upgraded aerial tramway with new cabins goes into summer season as planned
Today, the modernized Fellhornbahn I cable car opens its summer season after more than four months of renovations. Perhaps the biggest highlight for guests: floor-to-ceiling Plexiglas walls offer a magnificent panoramic view. But it's not just the cabins that are new...

Here are the technical measures at a glance:

  • Replacement of both large cabins
  • Replacement of the electric main drive and the diesel-hydraulic emergency drive
  • New hydraulic and controlled service and safety brakes
  • Overhaul of the gearboxes for the main and emergency drive
  • New cable car control system
  • Replacement of the cable guides on the supports
  • Installation of automatic sliding gates on the platforms for cabin exits
  • Special inspection for cable work: tensioning of the four suspension cables
  • Special inspections of the running gear and suspension arms
  • Special inspections of the drive wheels
  • A new shine for the surroundings*
    As part of the technical overhaul of the Fellhornbahn, the platforms (platforms) at the valley and mountain stations also received a new look. The platforms were not only visually modernized, but also promise improved quality for passengers and better occupational safety for employees. These are the main changes:
  • Renovation of the platforms at the valley and mountain stations
  • Redesign of the railings and walkways on the platforms
  • Visual redesign of the platforms
  • Occupational safety measures in accordance with current regulations: walkways, railings, platforms, stairs
  • Infrastructure measures: Redesign of office and control rooms, partial renewal of the building's electrical systems, heating, and thermal insulation
  • Fire protection measures as part of the modernization

Special thanks go once again to everyone involved, especially to the entire Fellhornbahn team. This project would not have been possible without you!

We wish you safe travels on the "new" Fellhornbahn I!

06/12/2025
Delivery and replacement of the new cabins

Today, the old large cabins on the Fellhornbahn I cable car were replaced with the new ones.
It was a very special moment for us when the two cabins met on the cable car...

"The video on YouTube": https://youtu.be/vTLg5jx4CXI

05/09/2025
Assembly of the main drive, brakes, emergency diesel and hydraulics

In addition, the new control cabinets were installed and painting work was carried out.

04/28/2025
Helicopter material flights to supports 1 and 2

Furthermore, cleanup work in the engine room is in full swing. The frames for the sliding doors on the platform have been concreted, and the insulation and plastering work in the control room and the electrical workshop has been completed.

04/18/2025
Removal of all technology from the engine room

At the same time, concrete sawing work has begun for the new doors and windows in the control room and the new electrical workshop in the valley.

Renovation work on the platform in the valley is progressing.

04/14/2025
Last transport trips on section 1 with old control

Today, the very last transports took place on the old FBO I large-cabin gondola lift.

After the last run, the electrical and mechanical control system was dismantled as planned.

New components were delivered, and the renovation of the platform is in full swing.

03/31/2025
2nd construction phase from 31 March 2025; duration approx. 14 weeks

• New drive motors
• New control system
• Visual redesign of the boarding areas
• Optimized occupational safety
• Optimized fire protection
• New cabins

03/30/2025
Last day of operation of the Fellhornbahn I

Last day of operation for the Fellhornbahn I
The end of the winter season also brought another conclusion: After more than 50 years of operation, the Fellhornbahn I had its last day of operation on Sunday, March 30, 2025. You'll find out what's next in this construction diary.

05/24/2024
Gearbox overhaul
05/22/2024
Re-bearing of the drive pulleys
05/20/2024
Factory revision

Factory Overhaul of the Suspension Arms

The suspension arms are the connecting component between the undercarriage and the cab. These are completely overhauled at the factory and inspected for any damage. Safety-relevant components are checked for damage using special testing procedures and replaced if necessary.

Factory Overhaul of Undercarriage 1
After Undercarriage 2 was already overhauled at the factory in 2020, it's now the turn of Undercarriage 1. It is disassembled at the factory into almost all of its individual parts.
Safety-relevant components are inspected for damage using a special testing procedure and replaced if necessary.

05/17/2024
Moving the supporting cables

The most heavily stressed section of the suspension cables (the bending area above the chain saddle - approximately 24 meters) must be cut every 12 years. To do this, the corresponding length is moved downhill from the reserve at the top station's bollard, and the end connection (casting cone) is recreated.

05/16/2024
The cabins are lifted by the rope

To enable the work, both cabins were lifted from the ropes using heavy equipment.

05/13/2024
1st construction phase: May 13 to July 5, 2024

As part of the upgrade of Section 1 of the aerial tramway, extensive preparatory overhaul work will be carried out this spring.

A further construction phase, including the construction of a new control system, drive and braking unit, new cabins, and a facelift of the stations, will be completed in spring or early summer 2025.

Safety comes first!
Therefore, the work extends beyond the legally required scope, and key components will undergo a factory overhaul at Garaventa in Switzerland.

The on-site work will be carried out by four external specialist technicians with the assistance of an average of four FBO specialists.

load old articles
Website
  • Deutschland
  • English
  • Nederlands
We use cookies
We and our partners use cookies and similar technologies to provide our website, analyze traffic, and display personalized content. Data may be transferred to third-party providers (e.g., in the USA). Your consent is voluntary and can be withdrawn at any time. For more information, please see our privacy policy.
Settings  ·  Privacy policy  ·  Imprint
back
Cookie settings
Cookies that are strictly necessary for the operation of the website. further details
Google Tag Manager
Purpose of use:

Einbindung von Google Analytics über den Google Tag Manager. Cookies von Google für die Generierung statischer Daten zur Analyse des Website-Verhaltens. Dieser Anbieter kann Ihre personenbezogenen Daten außerhalb des EWR/der EU übertragen, speichern oder verarbeiten. Diese Länder haben möglicherweise nicht das gleiche Datenschutzniveau und die Durchsetzung Ihrer Rechte kann eingeschränkt oder nicht möglich sein.

Anbieter: Google LLC (Vereinigte Staaten von Amerika)

Verwendete Technologien: Cookies

Rechtsgrundlage: Einwilligung (DSGVO 6.1.a)

Speicherdauer: Die Cookies werden bis zu 730 Tage gespeichert.

Datenschutzhinweise: https://policies.google.com/privacy?fg=1

The Trade Desk Websitepixel
Purpose of use:

Auf dieser Website werden mit der Technologie von The Trade Desk (TheTrade Desk Ltd, 1 Bartholomew Close, London EC1A 7BL, United Kingdom,  https://www.thetradedesk.com/) Daten zu Marketing- und Optimierungszwecken gesammelt und gespeichert. Aus diesen Daten können unter anderem pseudonymisierte Nutzerprofile erstellt werden. Hierzu können Browser-Cookies eingesetzt werden. Die mit der Technologie von The Trade Desk erhobenen Daten werden seitens The Trade Desk nicht dazu benutzt, den Besucher dieser Website persönlich zu identifizieren. Der Datenerhebung und -speicherung kann jederzeit mit Wirkung für die Zukunft hier widersprochen werden. Weitere Informationen zum Datenschutz von The Trade Desk finden Sie hier

Website
Purpose of use:

Unbedingt erforderliche Cookies gewährleisten Funktionen, ohne die Sie unsere Webseite nicht wie vorgesehen nutzen können.

Anbieter:
Diese Cookies werden von OBERSTDORF KLEINWALSERTAL Bergbahnen auf Basis des eingestezten Redaktionssystems Tramino angeboten.

verwendete Cookies:
Das Cookie »TraminoCartSession« dient zur Speicherung des Warenkorbs und der Gefällt-mir Angaben auf dieser Website. Das Cookie »TraminoSession« dient zur Speicherung einer Usersitzung, falls eine vorhanden ist. Das Cookie »Consent« dient zur Speicherung Ihrer Entscheidung hinsichtlich der Verwendung der Cookies.

Rechtsgrundlage: Berechtigtes Interesse (kein Opt-Out möglich) (DSGVO 6.1.f)

Speicherdauer: Die Cookies werden bis zu 1 Jahr gespeichert.

Cookies that are required to analyze and improve the use of the website and to display advertisements that are relevant to your interests. further details
MMC: Allgemeines Tracking Clubseite
Facebook Pixel
Purpose of use:

Eine Tracking-Technologie, welche von Facebook und Facebook-Diensten verwendet wird. Dieser Anbieter kann Ihre personenbezogenen Daten außerhalb des EWR/der EU übertragen, speichern oder verarbeiten. Diese Länder haben möglicherweise nicht das gleiche Datenschutzniveau und die Durchsetzung Ihrer Rechte kann eingeschränkt oder nicht möglich sein.

Anbieter: Meta Platforms Ireland Ltd. / Meta Platforms, Inc. (Vereinigte Staaten von Amerika)

Verwendete Technologien: Cookies

verwendete Cookies:_fpd,_fbc

Rechtsgrundlage: Einwilligung (DSGVO 6.1.a)

Speicherdauer: Die Cookies werden bis zu 400 Tage gespeichert.

Datenschutzhinweise: https://de-de.facebook.com/privacy/explanation

Onlim Chatprogramm
Purpose of use:

Chatprogramm von Onlim. Ermöglicht dem Besucher einen Chat auf der Webseite.
Anbieter: Onlim GmbH (Österreich)

Verwendete Technologien: Cookies
Datenschutzhinweise: https://onlim.com/datenschutzerklaerung/

Externer Videodienst YouTube
Purpose of use:

Cookies die benötigt werden um YouTube Videos auf der Webseite zu integrieren und vom Benutzer abgespielt werden können. Dieser Anbieter kann Ihre personenbezogenen Daten außerhalb des EWR/der EU übertragen, speichern oder verarbeiten. Diese Länder haben möglicherweise nicht das gleiche Datenschutzniveau und die Durchsetzung Ihrer Rechte kann eingeschränkt oder nicht möglich sein.

Anbieter: Google LLC (Vereinigte Staaten von Amerika)

Verwendte Technologien: Cookies

Rechtsgrundlage: Einwilligung (DSGVO 6.1.a)

Speicherdauer: Die Cookies werden bis zu 179 Tage gespeichert.

Datenschutzerklärung: https://policies.google.com/privacy?hl=de&gl=de

Externer Videodienst Vimeo
Purpose of use:

Cookies die benötigt werden um Vimeo Videos auf der Webseite zu integrieren und vom Benutzer abgespielt werden können. Dieser Anbieter kann Ihre personenbezogenen Daten außerhalb des EWR/der EU übertragen, speichern oder verarbeiten. Diese Länder haben möglicherweise nicht das gleiche Datenschutzniveau und die Durchsetzung Ihrer Rechte kann eingeschränkt oder nicht möglich sein.

Anbieter: Vimeo LLC (Vereinigte Staaten von Amerika)

Verwendte Technologien: Cookies

Rechtsgrundlage: Einwilligung (DSGVO 6.1.a)

Speicherdauer: Die Cookies werden bis zu 1 Jahr gespeichert.

Datenschutzerklärung: https://vimeo.com/privacy